2.26MW Photovoltaic Power Generation Project
The enterprise is mainly engaged in the R&D and sales of non-metallic nanomaterials, headquartered in Hong Kong, and is a high-tech enterprise with a wide range of cooperative projects with the Chinese Academy of Sciences and other key research institutes at home and abroad.
The enterprise has a building area of 14,000 square meters, with an effective usable area of 13,500 square meters, and an annual electricity consumption of about 7 million kWh/year before the installation of the photovoltaic project. After the installation of the PV project, the average annual income reaches 1.6533 million yuan, and the capital can be recovered in 4 years.
Project Overview
Installed capacity: 2260KW
Annual power generation: 2.047 million KWH
Self-generation and self-consumption ratio: 85
Desulfurization coal tariff: RMB 0.453/KWH
Annual revenue: 1.6533 million
Payback period: 4.5 years
Project Benefits
Environmental benefits: reduce carbon dust by 12,300 tons, carbon dioxide by 45,600 tons, sulfur dioxide by 0.12 million tons, and cut down 2.52 million trees.
Social benefits: using idle roofs to build photovoltaic power stations, keeping warm in winter and cooling in summer, and prolonging the life of factory roofs.
Project benefits: 25 years total income of 41.33 million yuan